Tag Archive for Enercon

King Willem-Alexander opens Krammer Wind Farm

Yesterday, May 15, the official opening of Krammer Wind Farm took place. The wind farm, located on and around the primary flood defence Krammersluizen, on the border of the provinces of Zuid-Holland and Zeeland, was opened by King Willem-Alexander, in the presence of over 700 guests. It was the start of a 4-days celebration for…

Zeewolde Wind Farm to deploy Enercon new EP3 turbines

Wind Park Zeewolde B.V. (WPZ) has signed a contract with German wind turbine manufacturer Enercon for the supply of 74 of Enercon’s new EP3 type turbines and 9 turbines of the existing EP2. In addition, a long-term Operations and Maintenance contract is closed. The largest EP3 turbines are 4.2 MW and have a tip height…

All purchasing contracts in place for Zeewolde Wind Farm

Wind Park Zeewolde B.V. has concluded all necessary purchasing contracts to realise the largest onshore wind farm in the Netherlands. The contracts have a total value of approximately 400 million Euros. In addition, a 15-year sales contract for the produced electricity is concluded. The purchase contract for more than 320 MW of turbines has been…

Groundbreaking ceremony for Windpark de Veenwieken

On april 1, a groundbreaking ceremony took place to mark the start of the construction of the onshore wind farm De Veenwieken. Eelco Bots, director of Windunie Development, together with the councillor of Hardenberg (Jan ten Cate), the councillor of Ommen (Bart Jaspers Faijer) and Arthur Vermeulen of Raedthuys, symbolically hit the first pile into…

All turbines at Windpark Samen Voor de Wind dismantled

All 7 wind turbines at Windpark Samen Voor de Wind are now dismantled. The old turbines will be replaced by modern, larger turbines. The onshore wind farm comprised of 7 Enercon, type E66, turbines which have been operating since 2002 alongside the Overijsselse tocht, nearby Swifterbant in the municipality of Dronten. Windpark Samen Voor de…

Start construction Windpark De Veenwieken

This month, the first construction activities will start at the 30 MW onshore wind farm Windpark De Veenwieken, located in an area between the municipalities of Ommen and Hardenberg. The construction activities include road construction and connection activities. The road construction will be performed by KWS Infra. The company will also construct the stand place…

All turbines installed at Windpark Krammer

Last week, the last of the 34 Enercon E 115 wind turbines was installed at Windpark Krammer. 25 turbines have already been commissioned. In the next few months, commissioning activities of the turbines will take place. The 102 MW wind farm is expected to be fully operational by the end of March, 2019. The official opening…

Financiering Windpark Spui rond

De Nederlandse Yard Energy Group en de Japanse Eurus Energy Group hebben de financiering rond van Windpark Spui, dat nabij het Zuid-Hollandse Korendijk zal verrijzen. Het windpark krijgt een vermogen van 21 MW en zal bestaan uit vijf Enercon E-126 EP4 windturbines met elk een vermogen van 4,2 MW. De 135 m hoge windturbines hebben…

Waterstof voor de van-wind-tot-wiel-keten

Op de proeflocatie van ECN in de Wieringermeer moet in het eerste kwartaal van 2019 een 4,8 MW-windturbine staan, die naast elektriciteit ook waterstof produceert. De turbine van Lagerwey wordt een geïntegreerde installatie die de opgewekte stroom direct gebruikt om water om te zetten in waterstof en zuurstof. Op het testveld zal de elektrolyse-installatie nog naast…

Enercon test prototype in Lelystad

Windturbinefabrikant Enercon heeft in Lelystad zijn nieuwe prototype E-126 EP4 geïnstalleerd. Het is het eerste model uit het nieuwe 4 MW-platform van de producent. Met een ashoogte van 135 meter kan de E-126 EP4 op locaties in het binnenland bij een gemiddelde windsnelheid van 7,5 meter per seconde zo’n 14,8 miljoen kWh opwekken. Medio 2016…